Since the October 28, 2024the north access ramp to the town of Valognes (Manche) by the RN13 east closed in order to make a roundabout on the RD974 au lieu-dit Fosse Prémesnil.
The construction site was planned until January 17, 2025.
4 and a half months of construction
Except that the website bison-fute.gouv.fr managed by the state services reported a new deadline: the 14 mars 2025.
When asked, the services of the Department of Manche confirmed the information: “Indeed, the construction site took delay . The snowy episode has soaked roadway structures currently being built and they were no longer able to provide the required lift. It is therefore necessary to let drying time before you can continue. »
No asphalt production in January
“Moreover, the month of January is a month traditionally dedicated to maintenance asphalt production stations. These are therefore closed until the end of January and no productionis not possible before this date. The construction site will not resume until the end of January,” add the Department’s services.
Cet layoutof a amount of 580,000 euros is financed by the Agglo Cotentin for 535 000 euros and by the Department of Manche for 45,000 euros.
For the development of the Armanville activity zone
Project management falls to the Department of Manche, which explained in La Presse de la Manche of October 29, 2024 that “ the Cotentin urban community wished secure access in the future Armanville craft zone in Valognes (Editor's note: more precisely the extension of this activity zone). »
3,500 vehicles per day are already passing through this location, even before the extension of the activity zone. This is why it was “decided to build a roundabout at the intersection of the RN13, RD974, Bretonnerie roadand the artisanal zone route. »
Technically “the development consists of the creation of a roundabout with four branches of 20 meters in radius, large enough to allow the passage of heavy goods vehiclesand the creation of a parking area . ” THE works are entrusted to the construction company Colas, one of whose agencies is based a few kilometers away, in Brix.
In our edition of November 9, we also recalled that the Armanville activity zone could become an advanced post of the port of Cherbourg with a space which would be developed over 2 hectares to accommodate heavy goods vehicles in transit for Irelandor England .
About 2 kilometers to the south, near the Les Bains du Cotentin aquatic center, the project to complete the current half-interchange between the RN13 and theRD902(the departmental road which connects Valognes to Bricquebec) is also still in the pipeline.