This “planned renovation” project involved nearly 11 km of HTA network (High Voltage – 20,000 volts) in the municipalities of Coulonces and Beaumesnil (). The operation consisted of changing all the parts presenting wear points : supports, insulators, fittings, anchors, surge arresters, switches, etc. Every 3 years, a helicopter and drones fly over the network to identify faults and damaged elements.

A long and careful preparation

The large-scale intervention, prepared for two yearsmobilized a thirty speakers came from Bayeux, Flers and Condé. Considerable work had been carried out upstream in order to “ minimize the impact of the outage and avoid inconvenience for users, by keeping the network under tension as much as possible and using generators as little as possible,” indicated Sylvain Dubois, technician at the Condé operational base for Enedis.

This project, which represents a total investment of 152 000 €, financed by Enedis, made it possible to secure and improve the quality of electricity supply to the 1,140 customers in the sector. This partial renewal process, which concerns air networksaims, through targeted actions, to extend the lifespan of the structures by at least 25 years.

“This work, which is part of a multi-year framework, is carried out thanks to a concession contract linking Enedis and the SDEC Energie, Calvados Departmental Energy Union which brings together all the municipalities, the latter being owners of their network, explained Catherine Gournet-Leconte, president of the SDEC. We are in a logic of territorial planning and territorial solidarity.”

Sylvain Dubois, technician at the Condé operational base for Enedis: “Upstream, teams placed equipment at the foot of each support to reduce intervention time.” ©The Voice Le Bocage
Videos: currently on Actu
The line was de-energized and cables ensured the safety of the disconnected personnel. ©The Voice Le Bocage
Bernard Clouard, deputy mayor of Beaumesnil, Gilles Maloisel, deputy mayor of Coulonces, Frédéric Hardouin, Calvados territorial delegate at Enedis, and Catherine Gournet-Leconte president of SDEC Energie.
Bernard Clouard, deputy mayor of Beaumesnil, Gilles Maloisel, deputy mayor of Coulonces, Frédéric Hardouin, Calvados territorial delegate at Enedis, and Catherine Gournet-Leconte president of SDEC Energie. ©The Voice Le Bocage

“Train our young people”

Furthermore, this maintenance work is an opportunity to “train our young people”underlined Frédéric Hardouin, Calvados territorial delegate at Enedis. A partnership was established for this purpose with the high schools of Condé and Bayeux. “The company is recruiting many work-study studentsspecifies Axelle Morineau, Privileged Contact for Bocage Virois for Enedis. We take advantage of this type of project to improve young people’s skills, thanks to mixed teams.”

The intervention was completed in the afternoon. Some operations made impossible by the crops will be carried out later, under tension, by technicians.