The burying of the networks resulted in the creation of 622 linear meters of trenches in the public space, the laying of 913 linear meters of underground public electrical distribution cables, 360 linear meters of underground public lighting cables, 7 public lighting lanterns and 1,690 linear meters of PVC pipes for telephony (Orange copper and fiber cables).
The removal of 586 linear meters of overhead public electrical distribution networks and connections, 7 supports and 6 metal brackets on the facades was carried out in the heart of the village.
A large part of the asphalt from the hamlet of Reynier was used as part of this project.
-The financial breakdown of the construction site
The financial expenditure is divided between the own funds of TE-SDE04 and those of the municipality. Indeed, for the study and rural electrification work, as well as for the resumption of the public lighting function, it was TE-SDE04 which financed them with its own funds. Concerning the telecoms and public lighting works, the municipality reimbursed TE-SDE04 the amount advanced.