the evolution of 22 months of work in three minutes

the evolution of 22 months of work in three minutes
the evolution of 22 months of work in three minutes

Par

Editorial Landes

Published on

Nov. 4, 2024 at 1:15 p.m.

See my news
Follow News Landes

The Landes department unveiled a few days ago the time-lapse (accelerated video) of the work on the Pont de Sorde-l’Abbaye above the Gave d'Oloron, which lasted almost two years and whose reopening was made official on July 22. In the images, we can see from A to Z this project which cost 5.7 million euros.

270 tonnes of reinforcement, 109.8 meters long

The structure, 110 meters long, was rebuilt identically with four piers and five bays, and a 6 meter wide roadway. It had been classified 3U according to the IQOA (Image Quality of Works of ) rating, corresponding to “a work whose structure is seriously damaged and requiring urgent repair work” explained the Landes department at the time.

During this work, Compensatory measures have also been planned for the house martin and the common kestrel“two protected species recorded on the site” namely 61 artificial nests for the swallow and a nest box for the falcon.

Characteristics of the work:

  • Total length of the structure: 109.8 m
  • Overall width of the structure: 8.88 m
  • Road width: 6.00 m
  • Width of sidewalks: 0.9 m (upstream) and 1.3 m (downstream)
  • Deck thickness: beam (85 cm) + slab (27 cm) = 1.12 m
  • Number of supports in minor bed: 3
  • Guardrail: metal
  • Deep foundations: 26 piles
  • 270 tonnes of reinforcement
  • 1500 m3 of concrete

Follow all the news from your favorite cities and media by subscribing to Mon Actu.

-

-

PREV His tractor falls eight meters, a teenager seriously injured
NEXT All Saints' Day holidays in Gironde: surfing, cycling and salted butter rusks at the Porge Océan municipal campsite