Development work on Boulevard Pierre de Garidel

Development work on Boulevard Pierre de Garidel
Development work on Boulevard Pierre de Garidel

As part of the work on the Multimodal Interchange Hub, the City is undertaking development work on Boulevard Pierre Garidel.

The construction site is made up of 3 main parts:

1. Creation of the rainwater network, the drinking water network, the municipal fiber network

Phase 1 from 06/24 to 08/09: night work on closed road from 8 p.m. to 6 a.m.

Phase 2 from 08/07 to 2/08: daytime works on closed roadAccess to the station car park will be via Avenue de la Libération.

2. Demolition of curbs, sidewalks, earthworks of the road, stonework in GNT

Phase 3 from 08/12 to 09/06: night work on closed road from 8 p.m. to 6 a.m.

3. Creation of borders, GNT adjustment, creation of coating

Phase 4 from 09/09 to 27/09: night work on closed road from 8 p.m. to 6 a.m.

Phase 5 from 09/30 to 10/11: daytime work on closed roadAccess to the station car park will be via Avenue de la Libération.

Phase 6 from 10/14 to 10/18: night work on closed road. No access to the station car park

-

-