As part of the work on the Multimodal Interchange Hub, the City is undertaking development work on Boulevard Pierre Garidel.
The construction site is made up of 3 main parts:
1. Creation of the rainwater network, the drinking water network, the municipal fiber network
Phase 1 from 06/24 to 08/09: night work on closed road from 8 p.m. to 6 a.m.
Phase 2 from 08/07 to 2/08: daytime works on closed roadAccess to the station car park will be via Avenue de la Libération.
2. Demolition of curbs, sidewalks, earthworks of the road, stonework in GNT
Phase 3 from 08/12 to 09/06: night work on closed road from 8 p.m. to 6 a.m.
3. Creation of borders, GNT adjustment, creation of coating
Phase 4 from 09/09 to 27/09: night work on closed road from 8 p.m. to 6 a.m.
Phase 5 from 09/30 to 10/11: daytime work on closed roadAccess to the station car park will be via Avenue de la Libération.
Phase 6 from 10/14 to 10/18: night work on closed road. No access to the station car park