€1.9 million to redo 1.3 km of railway track

Par

Frank Baudouin

Published on

Nov. 20 2024 at 6:21 p.m

See my news
Follow Pontivy Journal

No more rails, no sleepers and even less ballast. Near Pontivy station (Morbihan), the railway now resembles a hiking trail. At least, for a few weeks…

The platform redone

Since the end of October, the Auray-Pontivy freight line has been under construction over 1.3 km, from Pontivy station towards the north.

This involves renewing the railway platform and carrying out hydraulic and sanitation work so that freight traffic can continue in complete safety.

SNCF Réseau communications department

The work is being carried out by the companies ETF and Olichon for an amount of 1.9 million euros, financed by the State and the Region.

Maintain and develop freight

Because this part of the line, between Pontivy and Saint-Gérand, was the most degraded, it was rebuilt in advance.

“This work is a prerequisite for the work which will take place in 2026-2027 as part of the State Region Plan Contract (2023-2027)”.

Videos: currently on Actu

The State Region plan contract plans to renew the freight capillary lines in Brittany (Auray-Pontivy and Vitré Gérard), for a total amount of 40.3 million euros.

The objective is to maintain and develop rail freight in Brittany in line with the national freight strategy.

SNCF Réseau communications department

Freight and tourism

The Auray-Pontivy-Saint-Gérand line is used all year round by the freight company Millet Rail for two clients: Sanders and the Le Gouessant cooperative.

In summer and for the end-of-year holidays, this line is used by the Napoléon Express tourist train of the Chemins de fer du Center-Bretagne association.

Work on this Pontivy part should be completed in early December 2024.