DayFR Euro

revegetation, car parks… A 1 million euro project for the Cliscouët district

Par

Morbihan Editorial

Published on

Dec 18 2024 at 11:50 a.m.

See my news
Follow News Morbihan

The Place de Faréham of Valves (Morbihan) will have the right to a makeover. “It has no soul, is not beautiful and is open to all drafts,” repeats Mayor David Robo on each of his trips to the Cliscouët district. The project of redevelopment of the place was presented to residents on Thursday December 12, 2024. What should we remember?

What scope is concerned?

The redevelopment will take place at Place de Faréham and Square du Ponant. Consultations were carried out between the end of 2022 and the summer of 2024.


Car park modifications

The big change is the opening of the parking lot under the Place de Faréham to all. Thus, 108 places will be available.

“Today, it is only open to Morbihan Habitat (MH) residents at the rate of €30/month. The occupancy rate is only 20%,” indicates the community.

After the work, this will become free for MH tenants. “It will be €30/month for traders and local residents,” specifies the community.

Videos: currently on Actu

On the other hand, for outdoor parking, there will be fewer parking spaces with greening: 35 places place de Faréham (compared to 75 currently), 8 places in Square du Ponnant and a 5-place drop-off point.

Greening the square

The place is a mineral space with uses that are difficult to identify. One of the objectives is to vegetate (planted space, furniture) by working on several identified places,” explained landscape architect Yannis Le Quintrec works on town planning projects in .

Here are some arrangements for the square du Ponant

  • A central meadow, with a 15 meter long concrete bench
  • Benches and benches
  • 3 mini urban forests
  • A multi-sports ground open to the square
  • A PMR table tennis table
  • A playground (net structure, cabin with slide, and a spring game)
  • A deserted pedestrianized school with distribution square and bicycle parking

And for the Faréham square:

  • Creation of a friendly urban garden square, made up of tree-filled plant islands, providing cool areas in summer and demineralizing this place.
  • Positioning of urban furniture: Benches, seats and tables
  • Conservation of parking on the edge of the square with the creation of 3 PRM spaces and a bicycle parking area.
  • Quality lighting of the place with low consumption LEDs
  • Maintenance of equipment allowing the reception of the Sunday market
  • Design designed to allow video protection to function properly.

New housing

As part of this project, the community sold land. New housing will emerge from the ground:

There will be four small houses, which represent eight housing units in total, and two small collectives for 15 to 20 housing units in total.

David Robo, mayor of Vannes

Accommodation accessible via real solidarity lease (BRS) will be possible in some of the accommodations.

What is the work schedule?

Initially, “major structural work” of preliminary reinforcement of the slab structure of the Place de Faréham are in the pipeline from January to February 2025:

  • Addition of posts and reinforcement of beams in the underground car park
  • Necessary limitation and adaptation of the costs of the landscaping project for Place de Faréham.

There will also be a stage of modernization of the underground car park (painting, lighting, creation of boxes and addition of posts).

Work schedule:

End of November 2024 to February 2025: installation of an exhibition on Fareham Square presenting the project
December 2024 to February 2025: modernization and reinforcement of the parking slab by Morbihan Habitat
Construction of Place Fareham second quarter 2025 – Delivery in June 2025
Construction of the Square du Ponant from April 2025 – Delivery in October 2025
From the second half of 2025: Thermal rehabilitation, renovation, improvement of PMR/aging of tenants, renovation and insulation of the facades of the Morbihan Habitat park and rehabilitation of the arcades in front of the shops and the passages between Place Fareham and Square du Ponant, as well as ‘between the Fareham pace and the Super U car park

The realization of the square du Ponant will be built from April 2025 for delivery in October 2025. “The work around the school and the car park will be carried out during school holidays. Access to the Salle des Alizés will be maintained for the duration of the work,” reassures the municipality.

For the realization of the Place de Faréhamconstruction will begin at second quarter 2025 for delivery in June 2025.

Place de Faréham in the Cliscouët district. ©Actu Morbihan

The total developments amount to 1,150,000 euros TTCi.e. 350,000 euros for the Place and 800,000 euros for the square.

Follow all the news from your favorite cities and media by subscribing to Mon Actu.

-

Related News :